Refurbishment of Swan Theatre and Classrooms

Project: Refurbishment of Swan Theatre and Classrooms
School/Division: Teaching
Location: Building 12, Wagga campus
Time line: November 2010 - January 2011
Project cost: $400,000
Building area: North wing 660m2 and South wing 278m2
Project Status: Current
Project contact: Paul Baker

Project Brief

The scope comprises of general refurbishment works as follows:

Classrooms and the Swan Theatre:

  • Upgrade of fire detection, fire escape signage and emergency lighting
  • Install new energy efficient lighting throughout and
  • New signage to CSU current Standards

Classrooms only:

  • Replace existing floor finishes
  • Replace existing entry doors and Western elevation glazing????
  • Provide electronic card access where appropriate
  • Removal of redundant services and
  • Installation of new Air Conditioning

Funding

Charles Sturt University (CSU) and the Federal Government???s Education Better Universities Renewal Funding (BURF)

Consultants

Project Director: Savills Project Management
Project Manager: CSU ??? Division of Facilities Management
Quantity Surveyor: WT Partnerships
Architect: Gardner Wetherill
Structural & Civil: Hughes Trueman
Building Services: Umow Lai
BCA & PCA: McKenzie Group
Accessibility: Morris Goding Accessibility Consulting
Landscape: IScape

Head contractor: Zauner Construction

Further information

Theatre and classroom layout (PDF)

Site management plan indicating worksites (PDF)