Bathurst Campus Bus Shelter

Project Snapshot

  • Location:
  • Cost: $107,700.00
  • Estimated Completion date:
    February 2018
  • Contact: Garry Crichton
  • Interruptions

    The bus timetable remains unchanged and the Division of Facilities Management anticipate no disruption to service.

WW Bus Shelter Impression

Scope

The Division of Facilities Management is rolling out the 2017 – 2019 planned program works that involves new Bus Shelters across CSU Campuses. The next of these works include a new Bus Shelter for Bathurst Campus. The bus shelter will be available for staff and students and will provide protection and safety from the elements such as rain, sun and wind.

Design Features

The bus shelter will enhance traffic movement and identity of the campus. The bus shelter will encourage staff and students to use sustainable public transport to travel to and from the University. The shelter will provide opportunities to market the campus image, branding, University related advertisement and educational related information.

Sustainability Features

  • Site selection - accessibility
  • Orientation – protection from prevailing weather conditions, with large windbreak panels
  • Shading – Aluminum roof extended cover
  • Natural ventilation - openGlazing – Toughen Safety Glass
  • Water - Selection of plants for landscaping with low water requirements
  • Materials - Integrated fit out (as opposed to shell & core) modular design
  • Waste management during construction
  • Waste collection co-mingle
  • Low VOC finishes powder coated
  • Minimal use of PVC's

Additional Information

Design / Fabricator: Stoddart Infrastructure
Managing Contractor: Joss FM

The Site Plan for this project can be downloaded for review.

Progress report

Currently in Delivery Phase.