Major Current Project
Construction of New Regional Inter-Professional Clinical Simulation Centre
| Project: | New Regional Inter-Professional Clinical Simulation Centre - W11 |
|---|---|
| School/Division: | School of Biomedical Sciences and School of Nursing |
| Location: | Bathurst campus |
| Time line: | January 2011 - August 2011 |
| Project cost: | $2,845,000 |
| Building area: | Building: 327 m2; Landscaping: 908 m2 |
| Project contact: | Maree Neary |
Project Brief
The works comprise the construction of a new Clinical Simulation Centre to be utilised by the Schools to enhance the skills and work-readiness of the University's graduates in its Nursing and Paramedic programs, using a facility that supports contemporary practice based learning.

Funding (supporting) statement
Charles Sturt University (CSU) and the Federal Government’s Capital Development Pool Program (CDP)
Consultants
Superintendent: Charles Sturt University
Superintendents Representative and Project Manager: Savills Project Management
Quantity Surveyor: WT Partnerships
Architect: Gardner Wetherill
Structural & Civil: Hughes Trueman
Building Services & AV: Umow Lai
BCA & PCA: McKenzie Group
Accessibility: Morris Goding Accessibility Consulting
Landscape: IScape
Head contractor: Hansen Yuncken
Additional Information
The temporary gravel carpark "Towers carpark" will be closed during the construction works. Carparking is available at CP10 and along Research Station Drive.
Construction work site layout plan 7Feb11 (pdf)