Work performed in establishing CSU Interact has been broken down into key deliverables:
Programme Major Deliverables
| Project | Target Completion Date | Status |
| 1. IT Admin | October 2008 |
Completed |
| 2. Tools and Sites | June 2009 |
In progress |
| 3. Mandatory Subject Information | April 2010 |
In Progress |
| 4. Online Submission and Assignment Marking | December 2009 |
In progress |
| 5. Eportfolio | June 2009 |
In Progress |
| 6. Sakai v2.5 Review | May 2008 |
Completed |
| 7. Gradebook | December 2009 |
In Progess |
| 8. Sakai 3 implementation | TBA |